21 September 2026

The Perfect Site Can Still Be the Wrong Site

On paper, Project Tomahawk had one of the characteristics data center developers prize most: power. White Rose Partners proposed a roughly 225,000-square-foot data center on 37.3 acres in Prosper, Texas. Immediately southeast of the property sat an existing Brazos Electric Power Cooperative substation, an infrastructure advantage that project representatives specifically cited when explaining why the site made sense. The project never reached the Prosper Town Council.


On September 1, the Planning and Zoning Commission voted 7 to 0 to recommend denial after residents spoke for more than an hour against the project. Town staff also received more than 400 comments opposing the proposal, and an opposition petition eventually gathered more than 2,000 signatures. 


One week later, White Rose Partners withdrew the application. Managing partner Jeff Eigenbrood summed up the decision in one sentence: “We don’t want to go into communities where we’re not wanted.” That statement carries broader implications for development.

Physical Feasibility Is Only Part of Site Selection

The traditional site selection checklist is familiar. Land. Power. Water. Fiber. Access. Zoning. Economics. Those factors still matter. But projects with unusually large infrastructure footprints increasingly require another category of diligence: political and community feasibility. Project Tomahawk demonstrates why.


The adjacent substation helped answer an important infrastructure question. It did not address the questions residents and commissioners were asking about electricity demand, noise, water use, compatibility with nearby development, or the potential effect on local utility costs.


White Rose Partners responded to some of those concerns. The project website stated that water use would be limited, noise would be mitigated, and the developer would comply with applicable requirements. The company also proposed a 65-decibel maximum at the property boundary. However, some key operational details remained unresolved.


Commissioners specifically asked about exact noise levels, the project's electrical requirements, and its potential impact on residents' electricity rates. Developer representatives explained that some of those details could not be finalized until later in the development process. That created a problem that is increasingly common in data center development.

Developers Need Flexibility. Communities Want Certainty.

A speculative data center developer may not know the ultimate tenant when a site enters entitlement.

That is not unusual. Different tenants can bring different equipment, cooling systems, power requirements, operating characteristics, and building specifications. Some decisions legitimately cannot be made until an end user is identified.


But communities increasingly view those unanswered questions differently. From the developer's perspective, flexibility preserves the ability to attract a tenant. From the community's perspective, flexibility can look like uncertainty. When residents are asked to approve a land use with potentially significant energy, noise, and infrastructure implications, uncertainty itself can become a reason for opposition. That appears to be one of Prosper's central tensions.


The developer needed enough entitlement flexibility to make the site marketable. Commissioners wanted enough operational specificity to understand what they were approving. Neither position is particularly surprising. The problem is what happens when that gap is first addressed at a public hearing.

The Real Due Diligence Starts Earlier

The lesson from Project Tomahawk is not that data centers cannot be built near growing communities. It is that site selection cannot end with physical feasibility.


A site may have available acreage, nearby transmission infrastructure, favorable economics, and a workable development plan, yet still be politically unbuildable. That risk should be evaluated before substantial capital, entitlement work, engineering, and public positioning are committed to a location. For major infrastructure projects, developers should be asking another set of questions alongside the engineering analysis: 


What does the community believe this land should become?

What concerns already exist about growth?

Who is likely to organize?

What information will residents expect before an entitlement hearing?

What questions cannot yet be answered?

And perhaps most important, how much uncertainty will the community tolerate?


Project Tomahawk looked attractive because of what surrounded the property physically. It ultimately became unviable because of what surrounded the property politically.

That distinction matters.


The perfect site can still be the wrong site.

Recent Posts

by Land Use Strategies 11 September 2026
CEQA Reform Did Not End the Search for Certainty
by Land Use Strategies 3 September 2026
California lawmakers sent Senate Bill 954 to the governor’s desk this week, and coverage has settled into a familiar pattern. Environmental groups call it a workable compromise, while business groups say it goes too far.
by Land Use Strategies 26 August 2026
Zoning is a parcel-based instrument. Drone delivery is a radius-based entitlement.
by Land Use Strategies 20 August 2026
For years, developers have treated community engagement as a part of the entitlement process. Pennsylvania has just moved it much closer to the front of the line.
by Land Use Strategies 12 August 2026
Reuters reported this week that the banks financing the U.S. data center boom have added a line to their diligence checklists: political and community opposition. Karen Fang, who runs infrastructure and sustainable finance at Bank of America, told Reuters she looks at two things: project readiness and credit quality. She defined readiness as the permits and approvals a project needs, plus the support of the people who will live around it. Research firm Data Center Watch counted at least 75 projects worth roughly $130 billion facing local opposition in the first quarter of 2026 alone.
by Land Use Strategies 3 August 2026
Beyond the Check: How to Turn a Community Benefits Agreement Into a Community "Yes"
What BP's Big Bronco solar project in Adams County actually teaches developers about winning entitle
by Land Use Strategies 21 July 2026
BP's Lightsource bp is moving its Big Bronco solar-and-storage project forward in Adams County, Colorado. The project totals roughly 300 megawatts of solar paired with 300 megawatts of battery storage and is backed by a reported $675 million in private investment. Public figures estimate $39 million in new local tax revenue and about 400 jobs at peak construction. By most accounts, it has been a smooth ride: willing landowners, a site that steers clear of sensitive areas, and little of the organized community opposition that stalls so many energy projects.
by Land Use Strategies 7 July 2026
In Central Oregon, the Deschutes River lives two lives. The stretch through Bend looks healthy. A mile or two downstream, roughly ninety percent of it vanishes into pipes and canals. A recent investigation by OPB and ProPublica followed the water to determine where it goes and who benefits.
Row of brick townhouses along a quiet street with parked cars and a vacant lot at the end
by Land Use Strategies 2 July 2026
In Lawrenceville, a developer plans to build 15 apartments on a 3,300-square-foot lot on 49th Street, next to Stinky's Bar and across from the Locomotive Lofts. It's tiny by headline-making standards, yet it now faces a formal protest before Pittsburgh's Zoning Board of Adjustment, backed by a neighborhood attorney, a
by Land Use Strategies 24 June 2026
What Arizona’s development battles reveal about the opposition every developer is about to face.
Show More